The state of commercial law in India is in doldrums. This is exemplified by a recent decision of the Supreme Court in Gangotri Enterprises v. Union of India (Civil Appeal No. 4814/2016 dt. 05.05.2016) which not only erroneous but against the settled principles regarding restraint of bank guarantees.

Some of the salient facts in the case are that Northern Railways wanted to encash bank guarantee given by the Contractor in respect of a contract which was apparently satisfactorily performed. Northern Railways wanted to do so in respect an alleged breach of another contract. Northern Railways took support of a clause in the Contract which entitled it to encash bank guarantees given under a contract to set-off “any moneys… due” under that contract or any other contract.

The Contractor approached the court to restrain Northern Railways from encashing the bank guarantee. The question went up to the Supreme Court. The Supreme Court held, inter alia, the following:

  • The sum due meant a sum for which is presently payable and due and therefore, such sums may be recovered from the security deposit only if the sum which is to be set-off is payable. Northern Railways has sought encashment in respect of an amount which is in the nature of damages. But the Contractor has disputed the same and is a subject matter of an arbitration.

  • Sum sought to be recovered was in respect of a contract distinct from the contract under which the bank guarantee was furnished.

On the basis of the above, the Court concluded that there was “a prima facie case in their favour for granting of injunction against the respondents so also they have made out a case of balance of convenience and irreparable loss in their favour…”

It is humbly submitted that this decision is grossly erroneous. The decision of the Supreme Court does not seem to be a decision on injunction against bank guarantee but on a claim for damages for wrongful invocation of bank guarantee. Following are the reasons:

The Court has not taken into consideration the settled position of law that injunction will lie against bank guarantees only if there is fraud or special equities. In this case, no fraud was made out by the Contractor. Special equities would mean that the Contractor should establish that it would be impossible to reimburse himself even if he ultimately succeeds in a case for damages for wrongful invocation of bank guarantee. The Supreme Court in the instant case has not gone into such an enquiry at all!

It is well-established that the three pronged test of prima facie case, balance of convenience and irreparable loss would alone not be sufficient in the case of injunctions against bank guarantees but the petitioner should establish fraud or special equities.

The Supreme Court fell in gross error when it went on to the merits of correctness of the decision of Northern Railways in invoking the bank guarantee. This is not required in a proceeding relating to injunction against a bank guarantee.

For all these reasons, the decision of the Supreme Court is grossly erroneous and has to be held per incurium. The decision of the Supreme Court is binding on all courts in India. This decision is likely to be cited in several courts in India in support of injunction against bank guarantees thereby undermining the sanctity of bank guarantees and thereby commerce. It is sad that when there is an urgent pressing need to overhaul commercial law in India, decisions like these take the Indian legal system several steps backwards.

First published here.

Original author: Badrinath Srinivasan

Comments

George11 20 May 2016, 13:21
+4 -0
I have to respectfully disagree. The Fraud or special equities rule applies when the bank guarantee is given under the same contract. If a contractor provides a bank guarantee in a contract for construction of a bridge, that does not mean it should be encashed in relation to dispute in some other contract say for supply of cement. The crucial distinguishing factor, which the Supreme Court has identified, was that bank guarantee sought to be encashed was not part of a disputed transaction, it was part of a satisfactorily completed contract.
Badrinath Srinivasan 20 May 2016, 15:01
+0 -0
George11, it depends on the terms of the contract. Ordinarily government contracts provide for a term enabling them to receover any dues under a contract by encashing the Security Deposit furnished under that contract or any other contract. Notwithstanding the existence or non-existence of such a condition, it is for a court hearing the case for damages for wrongful invocation to decide. I still stand by the views of the aforesaid post.

Now, going further, assume, hypothetically, that a clause like I suggest in this comment existst. If the Contractor raises a similar objection (that the Security was furnished under some other Contract), going by the SC judgement, the court has to construe the contractual term in an application for temporary injunction/ section 9 application, which is not within its domain.

The correct law is and should be that except in case of special equities and fraud, in no other case should BG invocation be restrained. Also, where ad interim relief is sought in such applications pending disposal on grounds of fraud or special equities, and such party is unable to establish it, the party must be burdened with indemnity costs.
Non-sensational 20 May 2016, 17:54
+2 -0
Do not agree with the interpretation. The judgement does not deal with the law of bank guarantees, much less, alter it - as suggested in the report.

The judgement is based on the interpretation of clause 62 (Gangotri Contract) and Clause 18 (DGS&D Contract). The report seems to suggest that the author has analysed both the contracts, but that analysis is missing in the report. The issue dealt with here seems more to be whether BG can be invoked in case a dispute arises in a different contract under which no BG is furnished.

The principles for injunction against invocation remains the same. The sanctity of the Bank Guarantees, in my opinion, has not been diluted.

I don't know what was argued during the proceedings, but could have been argued differently and the judgement could also have been written differently. It could have been possible to argue that invocation of the BG on account of the dispute arising from a different contract was fraudulent, and seek an injunction on that basis. But this is only speculative, one is not aware of the facts and circumstances.

It may be useful to keep interpretations and news updates separate. Reporting must be strictly accurate, without he author's interpretation (which could be debatable).
Badrinath Srinivasan 21 May 2016, 01:05
+0 -0
Non-sensational, LI sources posts from other blogs such as mine where such views on legal developments are posted. In fact, the above post was originally posted in http://practicalacademic.blogspot.com/2016/05/supreme-court-undermines-sanctity-of.html as is clearly noted above. So, this post above is not really a news report but a comment on a legal development.

Now on the correctness of the views expressed above, you are absolutely right in that the SC decision goes on to interpret Article 62 of the Contract. This is exactly where the SC goes absolutely wrong. In the determination of whether grounds exist for restraining BG Invocation, a court cannot go to interpret a term of contract except to determine whether there is fraud or special inequities. This seems to be the legal position in prominent jurisdictions such as England & Wales, several jusridictions in USA, etc.

Non-sensational, Gangotri couldn't have taken the fraud ground because there was no element of concealment or deliberate misrepresentation here, at least the judgement does not say so.

Now, what is the ex post impact of Gangotri: Most of the Government Contracts have a clause allowing it to recover dues from SD/ from dues to Contractor. Every time the issue regarding restraint of BG invocation comes up, the court will decide on whether the invocation sought was correct or not by going into the merits, thereby considerably delaying the effectivess of the BG as a security. Government, then, would rather prefer to have the SD amount as cash, which again would result in several tax related issues and cash flow issues to Contractors.
Badrinath Srinivasan 21 May 2016, 06:13
+0 -0
Non-sensational & George11, it is of immense importance that Raman Iron Foundry was overruled by a three judge Bench of the Supreme Court in HM Kamaluddin Ansari AIR 1984 SC 29, where the three judge Bench held that under clause 18, "it was enough if there was a mere claim on the part of the purchaser for payment of a sum of money by the contractor irrespective of the fact whether such sum of money was presently due and payable or not". Thus, the Supreme Court in Gangotri seems to have not only ignored the settled principles of BG invocation but also seems to have failed to consider the decision of the Supreme Court in Kamaluddin Ansari where it was ultimately held that Union of India could WITHHOLD such an amount or refuse to pay it (but cannot appropriate it). Hence, on merits, the same could apply in respect of BG as well.
Non-sensational 22 May 2016, 03:26
+0 -0
All of this is conjecture, unless we know the terms of the BG. May be a good idea to look at that. The SC has not reproduced it in the judgement.
Badrinath Srinivasan 23 May 2016, 07:37
+0 -0
Non-sensational, I do not think that the criticisms against this decision can be brushed aside as being merely conjectural. These criticisms are valid. To me, the most shocking thing about the judgement is reliance by the Supreme Court on an overruled decision (Raman Iron Foundry) which I found absolutely perplexing. Kamaluddin Ansari(AIR 1984 SC 29) clearly overrules it almost on all counts, especially on the interpretation of Clause 18. In fact, in Kamaluddin Ansari the SC states: "[Clause 18] unequivocally contemplates a claim for the payment and its is open to the Union of India to appropriate any amount due to the contractor under other pending bills. It does not contemplate the amount due and, therefore, the heading of this clause which talks of only 'Recovery of sum due' will not control Clause 18." The court clarified that it was not necessary that the claim on damages should be payable as determined by a court of law or as admitted, "it was enough if there was a mere claim..." Consequently, SC in Gangotri Enterprises not only decided the issue on merits (which it should never have done in the first place) but also relied on an overruled precedent to do so! This is no conjecture, I believe.
Bored 6 Jun 2016, 10:35
+1 -0
Even Worse, in Para 43 - "The case at hand was
similar on facts with that of the case of Union of India
(DGS&D) (supra) and hence the law laid down in that
case was applicable to this case. Even in this Court,
both the learned counsel did not bring to our notice
the law laid down in Union of India (DGS&D) case
(supra).

The case referred to as Union of India (DGS&D) is Raman Iron Foundry, which as the author points out has been overuled
Bored 6 Jun 2016, 10:55
+1 -0
So the Court relied on an over-ruled judgment (Raman) without any discussion of the decision of the larger bench (Kamaluddin Ansari). I appreciate that a judgment may be over-ruled on one point but may still be good law on another point but there is no analysis of any of this. It appears the Court was not even aware of Kamaluddin Ansari

It appears in effect that after arguments were heard, possibly a judicial clerk found Raman Iron Foundry and on a reading of this case alone, the Court proceeded to decide the issue without even considering Kamaluddin Ansari.

Scary....

Review ? Error apparent on face of record ?
Badrinath Srinivasan 6 Jun 2016, 11:31
+0 -0
Certain decisions seem to ignore the observations of the supreme court in kamaluddin on the correctness of Raman iron on the interpretation of the contractual provision. This I think is the reason why Raman iron is still thought t be good law.
Aneesh 6 Sept 2016, 11:34
+0 -0
Hi Badri.

Kindly look at the Intertoll judgment of the Delhi HC (2013) wherein it was discussed to what extent Raman Iron Foundry has been overruled.

The entire judgment is not bad law. Para 25 of Intertoll says: The decision in Raman Iron Foundry was overruled in M/s. H.M. Kamaluddin Ansari & Co. v. Union of India (1983) 4 SCC 417 on another point "that the clause in the contract applied to a claim itself and not only to an amount due". However, on the nature of the claim for damages the decision in Raman Iron Foundry has not been overruled and is good law."
B Srinivasan 6 Sept 2016, 12:41
+0 -0
Aneesh, you are correct. Intertoll and several other HC judgements make that distinction. Even the SC cites Raman Iron in several cases. Notwithstanding this, many High Courts question if Raman Iron still stands. To me, it is possible to take the argument that Raman Iron has not been overruled but is it good law? I doubt. At least the time has come to think judgements like Raman Iron, which., like many other judgements on contract law, seek to break settled contractual positions. These only bring uncertainty into substantive contract law and is one of the reasons why parties think twice in choosing Indian law as substantive law in international deals. The possible reason why Kamaluddin Ansari cannot be thought as having overruled Raman Iron is because the parties did not contest the interpretation of Raman Iron of the clause. But Kamaluddin Ansari definitely cast doubts on the interpretation of the relevant clause in Raman Iron.